How do I measure roofing for a takeoff?

Measure the roof on plan to the outside of the eaves, multiply by the pitch factor to get the slope area, then measure every flashing, capping and gutter in metres and count the downpipes and penetrations. Most misses are plan area priced as slope area, and cappings.

TL;DR: Measure the roof area on plan to the outside edge of the sheeting, then multiply by the pitch factor to get the true slope area in m². Measure ridges, hips, valleys, barges, flashings, cappings and gutters in metres, and count downpipes, sumps, overflows and penetrations. Read the pitch off the sections, the profile and insulation off the specification, and the drainage off the hydraulic drawings.

The roof plan says 1,200 m². The roofer's quote says 1,298 m².

Both are right. The roof is pitched at 22.5 degrees, so there's 98 m² more sheeting up there than the plan shows. That's an example, but it's the first thing I'd check on any roofing number.

What do you measure, and in what units?

A roof is an area, a set of edges and a set of counted items.

ItemUnitWhere it's measured
Roof sheeting or tilesm²Slope area, to the outside edge of the sheeting
Insulation, sarking, safety meshm²Slope area
Ridge and hip capping, valley guttersmAlong each line, on the slope
Barge and apron flashingsmEach raking edge and wall abutment
Parapet cappingsmTop of every parapet, girth noted
Eaves and box guttersmAlong the gutter line, size noted
Downpipesm or no.Counted on plan, length from the elevations
Sumps, rainwater heads, overflowsno.Hydraulic drawings and roof plan
Penetration flashings, skylights, hatchesno.Roof plan and mechanical drawings

Keep the units the same from level to level and block to block. Takeoff units of measurement covers why mixed units give you a total that means nothing.

How does the pitch factor work?

A plan shows the roof flat. The pitch factor converts plan area to slope area.

Slope area = plan area x pitch factor, and the pitch factor is 1 divided by the cosine of the pitch.

Roof pitchPitch factor
3 degrees1.001
5 degrees1.004
15 degrees1.035
22.5 degrees1.082
25 degrees1.103
30 degrees1.155

So 1,200 m² on plan at 22.5 degrees is 1,200 x 1.082 = 1,298 m².

At 3 degrees the factor barely moves the number. At 30 degrees it adds 15.5%.

If the pitches differ across the roof, split the plan into planes and factor each one.

Lengths need the same care. Ridges, eaves gutters and parapets run level, so the plan length is the real length. Barges, hips and valleys run up the slope. Measure each on plan, find the rise from the sections, and the true length is the square root of plan length squared plus rise squared.

What do I read off which drawing?

No single sheet has the whole roof on it.

The specification will often call up AS 1562.1:2018 for the design and installation of metal roof cladding and SA HB 39:2015, the installation code for metal roof and wall cladding. Roof drainage sits under AS/NZS 3500.3:2025. The laps, fixings and gutter sizes they lead to end up in the roofer's rate.

How do you measure flashings and cappings?

In metres, by type, with the girth written next to each one.

Girth is the width of the flat sheet before it's folded. A 300 girth barge flashing and a 600 girth parapet capping are different prices per metre, so 1 line called "flashings" is no use to anyone pricing it.

Walk the roof edge on the plan and give every condition its own line - eaves, barge, ridge, hip, valley, apron, parapet, box gutter. Then find the detail for each. If an edge has no detail, that's an RFI.

What gets missed on a roofing takeoff?

The same things most times.

Then check the roof against the rest of the takeoff. How to check a quantity takeoff has the cross-checks, and the waterproofing takeoff guide covers balconies and wet areas.

Can AI do a roofing takeoff?

It can do the measuring, and you check it.

CIM Build's AI takeoff measures lengths, areas and counts off the PDF drawings. You ask for the quantity in plain English, it calibrates each sheet's scale against the printed dimensions, and it returns a table with a marked-up copy of the sheet. In the bill of quantities each line sits under the scope item it measures, with the sheet or clause behind it.

For roofing, check whether an area is plan or slope, then open the markup on the cappings and gutters and see that every edge was picked up.

Book a briefing and bring the tender.

Frequently asked questions

Do I measure a roof on plan or on the slope? Measure it on plan, because that's what the drawing gives you, then convert to slope area with the pitch factor. The sheeting, insulation and sarking are all priced on slope area.

How much waste should I allow on roof sheeting? There's no single figure I can point you to. It depends on the sheet lengths, the roof shape and how many hips and valleys get cut. Ask the roofer what they've allowed, and keep waste separate from the net quantity so it's counted once.

Who measures the purlins and battens? It depends on the trade packages. Write it into the scope of works for the roofer and the steel fabricator so it's priced once.