Which units should each trade be measured in for a takeoff?

A table of the units Australian estimators commonly use for each trade - m, m², m³, tonnes and number - plus the 4 rules that stop a takeoff adding up to a number nobody can price.

TL;DR: Measure each trade in the unit its subcontractors price in. Concrete in m³, formwork in m², reinforcement and structural steel in tonnes, walls, ceilings, membranes and finishes in m², linear items like skirtings and flashings in m, and doors and fixtures by number. Where a bill of quantities has to follow a standard, the Australian and New Zealand Standard Method of Measurement (ANZSMM) sets the unit for each trade section.

The partitions on Level 1 came back as 412 m. Level 2 came back as 1,113 m².

Both numbers were right. Somebody added them together anyway, and the total went to a plasterer who priced it per m².

That's a made-up example, but mixed units are 1 of the quietest ways a takeoff goes wrong. So pick the unit per trade before anyone measures.

Which unit does each trade use?

These are the units most Australian commercial estimators measure in. Treat the table as common practice. Where the bill has to comply with the ANZSMM, the rule in the relevant trade section wins.

TradeMain unitAlso measured
Concretem³By element and strength grade. Surface finishes in m²
Formworkm² of contact faceSlab edges and narrow widths in m
ReinforcementtonnesMesh in m²
Structural steeltonnesHollow sections sometimes in m
Masonry and blockworkm²By thickness. Lintels and sills in m or number
Partitions and wall liningsm²By wall type, with the height stated
Ceilingsm²Bulkheads in m. Access panels by number
Waterproofing membranesm²Narrow strips and upturns in m
Tiling and floor finishesm²Skirtings, trims and stair nosings in m
Paintingm²Narrow items like frames and rails in m
Roofing and claddingm²Flashings, cappings and gutters in m
Doors and hardwarenumberBy door type and hardware set
Windows and glazingnumber or m²By window type
Services fixturesnumberPipe, duct and cable runs in m

A few of these are confirmed in public guidance. The NZIQS guidance notes to ANZSMM 2022 note that reinforcement and structural steel are measured in tonnes in the standard, that membranes are measured in m² with strips up to 250 mm wide in m, and that facade items are measured in m², m and number.

What is the ANZSMM?

The ANZSMM is the standard method of measurement for building works in Australia and New Zealand. The current edition is the second, ANZSMM 2022, and you can buy it from the Australian Institute of Quantity Surveyors.

It's organised by trade section. Each section says what gets measured, in which unit, and what's included in the item without being measured separately.

A quantity surveyor preparing a formal bill will usually follow it. A builder measuring its own trade bills at tender doesn't have to, unless the contract says so. More in the ANZSMM explained for builders.

Should partitions be measured in m or m²?

Either works. Pick 1 and hold it across every level.

Most plasterers price per m², so m² by wall type is the safer default. Some estimators measure length by wall type and state the height, because it's faster off a plan. That's fine as long as the height is on the line and the same method is used on every floor.

Divide the area by the length for each wall type and you should get a height that matches the sections. If you get 0.4, the units are mixed.

What rules keep the units straight?

4 of them.

  1. One unit per item, across the whole job. Set it before measuring starts and write it at the top of the trade.
  2. Put the missing dimension in the description. An area needs its thickness or type. A length needs its height or size. "W3 partition, 3.1 m high" can be priced. "W3 partition" in m can't.
  3. Measure net. Measure the work as fixed in place, and keep waste and laps in the rate. A quantity with waste added, priced at a rate with waste in it, has paid for the waste twice.
  4. Use the unit the subcontractor quotes in. If the steel fabricator quotes per tonne and your bill is in m, somebody converts it, and that's 1 more place for an error.

How do I check the units before pricing?

Sort the takeoff by trade and scan the unit column. It takes 5 minutes.

The rest of the checks are in how to check a quantity takeoff, and the steps to build the bill are in how to prepare a bill of quantities.

How does CIM Build handle units?

With CIM Build's AI takeoff you ask for the quantity in plain English - wall lengths by type, floor areas by finish, doors by fire rating - and it comes back as a table with a marked-up copy of the sheet.

In the bill of quantities every line carries its unit, its quantity and the sheet or clause it came from, under the scope item it measures. It exports to Excel, so you can check the unit column the same way.

Book a briefing and bring the tender.

Frequently asked questions

What unit is concrete measured in? Concrete is measured in m³, grouped by element and strength grade. Formwork is measured separately in m² of contact face, and reinforcement by the tonne.

What unit is reinforcement measured in? Reinforcing bar is measured by mass, in tonnes in Australia. Mesh is commonly measured in m². The bar schedule or the lengths and mass per metre should sit behind the figure.

Do I have to follow the ANZSMM for a takeoff? Only if the contract or the tender documents require it. A builder's own trade takeoff can use any consistent method, but the ANZSMM is the reference a quantity surveyor will use for a formal bill of quantities.

Should a takeoff include waste? No. Measure net and carry waste and laps in the rate or on a separate line, so it's only allowed once.