How do I test an AI bill of quantities against a professionally measured one?
A 7-step test for an AI bill of quantities against a bill measured by a quantity surveyor: same revision, same measurement rules, tolerance set before you look, then every difference traced to the sheet. Includes a table of why 2 bills differ.
TL;DR: Pick a job that already has a bill measured by a quantity surveyor, and run the AI on the same drawing revision and the same specification. Line the 2 bills up item by item, set your tolerance before you look at the results, and trace every difference outside it back to the sheet. Count the items that appear in only 1 bill. The measured bill can be wrong too, so the sheet settles each difference.
Say the QS bill for an 84-apartment job has 4,120 m² of internal partitions and the AI bill has 3,890 m².
That's 230 m² apart, about 5.6%. Is the AI short, or is the QS over?
You can't tell from the 2 numbers. You can tell in 10 minutes if both bills show what was measured and where. Here's how I'd run the test. The figures are made up.
Which job should I test on?
One that's finished tendering, with a bill you paid for and trust.
You want the drawing set and specification exactly as the QS had them, including the revision of every sheet. If the QS measured rev B and you give the AI rev C, you're testing the revision.
What has to match before I compare anything?
3 things, and skipping them is how a fair test turns into an argument.
The revision. Same sheets, same issue, same spec.
The measurement rules. A bill is measured to a method. In Australia that's commonly the ANZSMM, the Australian and New Zealand Standard Method of Measurement of Building Works, sold through the AIQS. A method of measurement sets the rules a bill is measured to, such as the unit for each item. Read the preambles of the QS bill, find out what rules it used, and ask the AI vendor what rules its bill follows.
The structure. One bill by trade and the other by element won't line up. Regroup 1 of them in Excel so each line has a partner. We cover the method in the ANZSMM explained for builders.
How do I run the comparison?
- Put both bills in 1 spreadsheet, QS quantity in 1 column and AI quantity in the next.
- Write down your tolerance per trade before you look at any differences.
- Calculate the difference on every line, in units and as a percentage.
- Mark every line outside tolerance.
- List the items that appear in only 1 bill.
- For each marked line, open the AI's markup and the QS's working, and find the cause on the sheet.
- Record the cause against the line.
Do step 2 before step 3. If you set the tolerance after you've seen the results, you'll set it wherever makes the result comfortable.
I can't give you a standard tolerance. Pick one per trade, and remember that a small percentage on the structure is more money than a big percentage on the letterboxes. So weight the review by cost. Check the 10 lines that carry the most money first.
Why would 2 bills of the same building differ?
| Cause | How to tell | Whose number to keep |
|---|---|---|
| Different measurement rule | The difference is the same proportion on every level, like openings deducted in 1 bill and measured through in the other | Whichever matches the rules you price to |
| Scale wrong on a sheet | 1 level is out by half or double and the others agree | The 1 with the scale checked against a printed dimension |
| An area missed | The markup stops short, or a room has nothing traced in it | The bill that measured it |
| Double counting | The same corridor or shaft wall appears under 2 items | The bill that counted it once |
| Different revision | The difference sits on sheets that were reissued | Neither. Rerun on the right set |
| Scope split differently | The totals across 2 trades agree and the trade lines don't | Either, once you know where the item sits |
| Item in 1 bill only | No partner line | Check the drawings and spec for whether the work exists |
Back to the partitions. Say the markup shows the AI stopped the corridor walls at the ceiling line and the QS measured them to the underside of the slab. 230 m² over 8 levels is under 30 m² a floor, and the wall type details show which height is right. Follow each difference like that until the sheet explains it.
The checks are the same ones in how to check a quantity takeoff.
What should I record at the end?
5 numbers and 1 opinion.
- Lines inside tolerance, out of the total.
- Lines outside tolerance where the AI was wrong.
- Lines outside tolerance where the QS bill was wrong.
- Items the AI found that the QS bill didn't have, and the other way round.
- Hours your estimator spent checking the AI bill.
The opinion is your estimator's. Could they check the lines that mattered from the markup, or did they end up measuring again?
That answer decides whether the tool saves time. If they had to measure again to trust it, it didn't.
Then load the next revision and see how each quantity moves. A tender bill gets measured more than once.
Where CIM Build fits
CIM Build reads the drawings and the specification into a scope of works for each trade, then measures the quantities against it to build that trade's bill of quantities. Every line carries its unit, its quantity and the sheet or clause it came from, and each line sits under the scope item it measures, so a scope item with no quantity stands out.
The measuring is done by AI takeoff, which calibrates each sheet's scale against the dimensions printed on it and returns a marked-up copy of the sheet. The bill exports to Excel, which is where you'd run the comparison above.
The estimator or quantity surveyor decides what is priced and signs it off.
Book a briefing and bring a tender with a measured bill.
Frequently asked questions
How close should an AI bill of quantities be to a QS-measured bill? There's no published figure I can point you to, and I won't quote one for CIM Build. It depends on the drawings. A sheet drawn to scale with dimensions measures well, and a sheet marked not to scale can't be measured reliably by anyone. Set your own tolerance per trade, write it down before the test, and weight it by cost.
Does an AI bill of quantities replace the quantity surveyor? No. The AI does the measuring and the first draft of the bill. A person decides what is priced, checks the lines that carry the most cost, and signs it off. On a job where the contract makes the bill a contract document, talk to your QS and your lawyer about who prepares it.