How do I measure concrete quantities from structural drawings?

Measure concrete in m³ by element and strength grade: plan area by thickness for slabs, section by length for beams and walls, section by height for columns. Formwork, finishes and joints are measured separately, and each volume is counted once.

TL;DR: Measure concrete in m³, split by element and by strength grade. Slabs are plan area by thickness, beams and walls are cross-section by length, and columns are cross-section by height between slabs. Take the grades from the structural general notes, the sizes from the plans and schedules, and make sure each volume is counted once where elements meet.

A typical floor measures 240 m³. The pour docket says 294.

The slab was measured at 200 mm across the whole floor plate. The band beams drop another 250 mm below it, and nobody added them.

It's a synthetic example. But 54 m³ a floor over 6 floors is 324 m³ of concrete, placed and paid for, that wasn't in the price.

What do I measure, and in what units?

Concrete is m³. The rest of the structure trade is measured around it.

Reinforcement is measured by weight and has its own method - see how reinforcement is measured for a bill of quantities.

Measure the volume net, as drawn. Over-ordering, pump line losses and waste go in the rate.

Which drawings and schedules do I read?

  1. The structural general notes. Strength grades by element, exposure, cover and any special mixes are on the first sheet or 2. Read them before measuring anything.
  2. The footing plan and footing schedule, for pad sizes and depths.
  3. The slab plans for each level. Thickness is usually a note or a hatch, with thickenings, drop panels and setdowns called up locally.
  4. The column schedule and the wall elevations, for sizes at each level. Columns often get smaller as the building goes up.
  5. The sections and details, for beam depths, hobs, upstands and steps in the slab.
  6. The architectural drawings, for anything concrete the structural set leaves out - plant plinths, kerbs, planter walls, stair landings.

Checking structural drawings against the architectural set is worth doing before the measure, because a setdown shown on one and missing from the other changes the volume.

How do I measure slabs, beams, columns and walls?

Slabs first. Measure the plan area of each thickness zone and multiply by the thickness.

Say a typical floor on a 6-storey apartment job is 1,200 m² at 200 mm. That's 240 m³.

Then the beams. Where a band beam sits under a slab you've already measured, only measure the downstand - the part below the slab soffit. Say there are 90 m of band beam, 2,400 wide, 450 deep overall. The downstand is 250 mm, so it's 90 by 2.4 by 0.25, which is 54 m³. Measure the full 450 and the slab thickness is counted twice.

Columns are the cross-section by the height from the top of the slab below to the underside of the slab above, by the number of columns. Take the number off the plan and the size off the column schedule for that level.

Walls are length by height by thickness, with the same rule at the slab. Core walls and shear walls usually carry a higher grade than the slabs, so keep them on their own line.

Do I deduct openings and penetrations?

Set the rule and state it.

A stair void or a lift shaft through a slab is a big opening and gets deducted on any method. Small penetrations for services are a different question, and the ANZSMM, sold by the AIQS, sets out what is and isn't deducted for a bill measured to it. If you're measuring for your own tender, write the rule at the top of the takeoff and give it to the subcontractors with the quantities.

What the ANZSMM is and when builders need it covers when it applies.

What gets missed?

Then cross-check. Divide the suspended slab volume by the floor area for a level. You should get a figure close to the slab thickness plus a bit for beams. If 2 typical floors differ, one of them is wrong. How to check a quantity takeoff before pricing has the full list of checks.

How does AI takeoff handle concrete?

CIM Build's AI takeoff measures lengths, areas, volumes and counts off the PDF drawing set. You ask for the quantity in plain English, it calibrates the scale on each sheet against the dimensions printed on it, and it returns a results table with a marked-up copy of the sheet. So you can see which slab zones were measured at which thickness, and check the ones that carry the most cost.

The bill of quantities carries each line in m, m², m³ or number, under the scope item it measures, cited to the drawing or specification clause it came from.

The estimator still checks the big lines and decides what's priced.

Book a briefing and bring the tender.

Frequently asked questions

Is concrete measured net or with waste? Net, as drawn. The supplier's order will be higher than the measured volume, and that difference belongs in the rate. Adding waste to the quantity as well doubles it.

How do I measure a column that runs through several floors? Floor by floor. Measure each lift from the top of the slab below to the underside of the slab above, using the column size from the schedule for that level. The slab thickness is already in the slab volume.

Do I measure concrete off the structural or the architectural drawings? The structural drawings, for sizes and grades. Then go through the architectural, hydraulic and mechanical drawings for concrete the structural engineer didn't draw - plinths, kerbs, hobs and planter walls. Where the 2 sets disagree on a size, raise an RFI.