← Back to blog
5 min read

Should a builder prepare its own trade bills of quantities at tender?

Yes, for the trades that carry the most cost and the ones where quotes are hardest to compare, if the drawings can be measured. You get quotes on the same quantities, your own number to check them against, and rates for later.

TL;DR: Yes, for the trades that carry the most cost and the trades where quotes are hardest to compare, as long as the drawings are complete enough to measure. A builder's own bill puts every subcontractor on the same quantities, gives you a measure to check their quotes against, and fixes rates you can use when a revision adds work. It costs estimator time, and your subcontract has to say who carries the quantities.

Say tender closes in 3 weeks on an 84-apartment job. The partitions package has gone to 4 subcontractors with the drawings and a 1-page scope letter, and each of them is about to measure the same building their own way.

You'll get 4 prices built on 4 different quantities. Then somebody on your team measures it anyway, at 9 pm, to work out which price is real.

So measure it first.

What is a builder's trade bill of quantities?

It's a bill of quantities the builder's estimating team prepares for 1 trade package. Each item of work has a description, a unit, a measured quantity and the sheet or clause it came from. It goes out with the trade package and the subcontractor puts a rate on each line.

A client's quantity surveyor sometimes issues a bill for the whole job. A builder's trade bill is smaller and written for the people who'll price that 1 trade. What a bill of quantities is covers both.

What does the builder get out of it?

The figures there are examples.

The last point is the one I'd weigh most. Work that no quote covered gets priced again on site, at a worse rate, and the margin pays for it.

What does it cost, and who carries the quantities?

It costs estimator time in the weeks when you have the least of it. How much depends on the trade and the state of the drawings, so I won't put a number on it.

The harder question is risk. If your bill says 13,650 m² and the drawings build out at 14,200 m², somebody pays for the 550 m².

A common setup is to issue the bill for the subcontractor's guidance, ask them to check the quantities against the drawings and tell you where they disagree, and let the package as a lump sum on the drawings and specification. Whether that wording does what you want depends on the subcontract. Read the clause on bills of quantities in your own form, and get a lawyer to look at it if the bill is going to be listed as a contract document.

Bill of quantities vs schedule of rates goes through how the quantity risk moves between the 2.

Which trades are worth measuring?

TradeWorth a builder's bill when
Partitions and ceilingsWall types, heights and reflected ceiling plans are documented
Floor finishes and tilingThe finishes schedule and the plans agree
WaterproofingWet area and balcony details are drawn
PaintingPartition and ceiling quantities already exist to build on
Doors and hardwareThere's a door schedule to count from
Concrete, formwork and reinforcementThe structural drawings are far enough along to measure
Services let as design and constructRarely. The subcontractor designs it, so they measure it

Start with the 3 or 4 packages that carry most of your trade cost. Add the ones where last time's quotes came back in 3 different formats.

Does a builder's bill need to follow the ANZSMM?

No, unless your tender documents or the contract say so.

A house format works for trade bills if it's the same across the trade - the same units, the same rule for openings, the same level of description on every line. What the ANZSMM is and when builders need it covers the cases where the standard method applies.

When should a builder skip the bill?

When the drawings can't be measured yet. On an early design, a bill gives every subcontractor a precise-looking number that the next revision will change. A schedule of rates or provisional quantities suit that stage better.

And skip it on small packages where 2 quotes and a clear scope letter do the job.

Where CIM Build fits

CIM Build reads the drawings and the specification into a scope of works for each trade, then measures the quantities against it to build that trade's bill of quantities. Every line carries its unit, its quantity and the sheet or clause it came from. The estimator checks the lines that matter, adds rates and exports the bill to Excel to send with the trade package.

When the quotes come back, CIM Build levels them against the same trade scope.

Book a briefing and bring the tender.

Frequently asked questions

Is a builder's bill of quantities a contract document? Only if the subcontract makes it one. A bill issued for guidance and a bill listed as a contract document carry different risk when a quantity turns out wrong. Your subcontract decides which you have, and a lawyer should check the wording.

Who should prepare the trade bill - an estimator or a quantity surveyor? Either can. A quantity surveyor brings a formal method and costs a fee, and the estimator knows how your subcontractors price. What matters is that the person who measured it records the source of every line and somebody else checks the biggest ones. How to check a quantity takeoff has the checks.

Should the subcontractor still measure the job themselves? Yes. Ask each subcontractor to check your quantities and list where they disagree. A subcontractor who queries a quantity has read the drawings, and their query is a free check on your bill.


Published by CIM Build. This is the text of https://www.cim.build/uk/blog/trade-bill-of-quantities-for-builders without the site design. Index of all pages. Contact.