What does an estimating workflow look like from tender to contract?
The 7 stages a builder's estimate goes through between the tender documents landing and the contract being signed, what each stage produces, and where scope goes missing between them.
TL;DR: A builder's estimate goes through 7 stages between the documents landing and the contract being signed. Register the documents, read them and raise RFIs, write a scope of works per trade, measure the quantities, get quotes and level them, build the price with its qualifications, then check the contract set against the set you priced. Each stage produces a document the next stage depends on, and most lost margin sits in the handovers between them.
Say an 84-apartment job lands on a Monday with a 4-week tender period. 600 drawings, a specification, 9 consultant reports and a set of Principal Project Requirements.
The workflow below is the order I'd run it in. The stages overlap on a real tender, but each one has an output, and if the output doesn't exist the next stage is working from memory.
What are the stages of an estimate from tender to contract?
| Stage | What it produces |
|---|---|
| 1. Register the documents | A drawing and document register with the revision of every sheet |
| 2. Read the set | An RFI list and a list of risks to price or qualify |
| 3. Scope each trade | A scope of works per trade package |
| 4. Measure | A takeoff or bill of quantities per trade |
| 5. Go to market | Subcontractor quotes, levelled against the scope |
| 6. Build the price | Trade totals, preliminaries, margin, qualifications and exclusions |
| 7. Tender to contract | A comparison of the contract set against the priced set |
What happens before any measuring starts?
Stages 1 and 2. Register every document with its revision and date, so that when someone asks in 6 months what you priced, the answer is a list.
Then read the set. The drawings, the specification and the reports all describe the same building and they often disagree. The acoustic report asks for a wall the drawings don't show. The PPR asks for a finish the schedule doesn't carry.
Each of those is an RFI while the tender is open. After it closes, it's scope somebody argues about. There's more on how to do the read in how to review tender documents and on what a gap looks like in what is a scope gap.
How do the scope of works and the takeoff fit together?
The scope of works says what each trade has to do. The takeoff says how much of it there is. Do them in that order.
If you measure first, the quantities only cover what the estimator thought to measure. If you scope first, every scope item needs a quantity next to it, and an item with no quantity is visible.
So for each trade package, write the scope from the drawings and the specification, with the sheet or clause behind each item. Then measure against it in the unit that trade prices in. The two together are the trade's bill of quantities. If you're doing this for the first time, how to prepare a bill of quantities covers the steps.
What happens when the quotes come back?
They come back in different formats with different inclusions. One plasterer has allowed for the fire-rated shaft walls and the other 2 haven't said.
Levelling is lining the quotes up against the same scope, item by item, so you can see what the low price left out. Then you decide how to carry each gap - add an allowance, ask the subcontractor, or qualify it in your offer. How to level subcontractor quotes goes through it.
If the subcontractors priced from your bill of quantities, this is quick. If each one measured the job their own way, you're comparing 3 different jobs.
What goes into the final price?
The levelled trade totals, your preliminaries, your margin, and the list of what the price assumes.
That last list matters as much as the number. Qualifications, exclusions, the drawing register you priced from, the RFIs that were answered and the ones that weren't. It's the record of what the price covers. Write it as you go, because nobody can rebuild it from memory in the last 2 days.
What changes between the tender and the contract?
Often the drawings. Weeks or months pass between the offer and the contract, the design keeps moving, and the set attached to the contract is frequently a later revision than the one you priced.
So before signing, compare the proposed contract set against the priced set, sheet by sheet, and list every change with what it does to scope. Each one gets priced, qualified or accepted on purpose. I've written that step up separately in how to compare tender drawings with contract drawings.
What the contract documents include, and which one wins when they conflict, is set by the contract itself. Standard forms like AS 4000 and AS 4902 deal with it in their own clauses and are usually amended. Your contract and your lawyer decide that. The estimator's job is to make sure the commercial team knows what changed before they do.
Then the job goes to the delivery team, with the scopes, the levelled quotes and the assumptions attached. That's covered in the estimating to delivery handover.
Where does CIM Build fit in the workflow?
CIM Build reads the drawings and the specification into a scope of works for each trade, with the sheet and clause behind every line. It then measures against that scope to build the trade's bill of quantities, which exports to Excel for rates.
When quotes come back, tender levelling reads each one against the trade scope and shows where one quote has allowed for work the others left out. The estimator decides how each gap is carried. And revision tracking compares drawing sets, which is the tender-to-contract check in stage 7.
Book a briefing and bring the tender.
Frequently asked questions
How long should each stage of an estimate take? There's no standard split, and it depends on the tender period and how many trades you're pricing. As an example, on a 4-week tender I'd want the register and the first read done in week 1, scopes and quantities out to market by the middle of week 2, quotes levelled in week 3, and the last week for the price and the qualifications. Addenda will push all of it.
Who owns the estimate after the tender goes in? The estimator, until the contract is signed and the job is handed to delivery. Post-tender clarifications and the tender-to-contract comparison both need the person who knows what was priced. After handover, the scopes and assumptions should travel with the job so the project team isn't guessing.